Quarterly Spending Report

Draft. Not approved for posting. First quarter figures rebuilt from the October 30 ledger. The period and payment checks are still needed.

FY2027 · July 1, 2026 to September 30, 2026

See the budget. See the costs.

The City Council asked for quarterly finance reports in Resolution 2026-117 on June 24, 2026. This page shows the water, sewer and storm drain part in plain language. It is updated after each report.

Track water, sewer and storm drain costs. Open a work area to see more. Use your browser’s Find tool to search the page.

Costs through September 30, 2026 · Provisional

At a glance

Annual plan · Part of the year

The service budgets match Where Your Money Goes.

Water

Annual service budget

$25.1M

$25,134,899 for FY2027

Full report budget: $28,668,681

Costs recorded$4,454,208.43

Includes loan interest. Principal paid is not shown.

Sewer and storm drains

Annual service budget

$30.7M

$30,702,940 for FY2027

Full report budget: $54,200,671

Costs recorded$3,836,628.85

Not counting sewer project costs. Includes loan interest. Principal paid is not shown.

Bills come at different times. Costs are added to the books at different times, too. Three months of costs may not be one quarter of the yearly budget.

Loan costs show interest only. Principal paid still needs a check. Sewer costs leave out project costs. The plan and costs do not cover all the same items. These totals do not show money left to spend.

See water by type of cost
Same budget groups as Where Your Money Goes. Loan costs are interest only.
Type of costAnnual service budgetCosts recorded
People$7,484,281.00$1,475,417.31
Loan payments$7,062,117.00$835,662.07Interest only
Repairs and replacement$4,169,037.00$851,633.87
Other costs$3,032,299.00$897,702.04
Power and chemicals$2,726,621.00$393,793.14
City services$660,544.00$0.00
See sewer and storm drains by type of cost
Same budget groups as Where Your Money Goes. Loan costs are interest only.
Type of costAnnual service budgetCosts recorded
Run the sewer plant$8,385,326.00$1,329,246.18
Repairs and replacement$7,668,296.00Not available
Loan payments$6,278,127.00$681,837.04Interest only
People$3,503,452.00$455,942.67
Other costs$2,953,536.00$755,233.31
City services$1,040,224.00$432,894.00
Electricity$873,979.00$181,475.65

ONE BUDGET · TWO VIEWS

Match the full report

The full report also counts wear and tear and more sewer projects. Those items are not in the service budgets above.

  1. Service budgets shown above$55,837,839
  2. Wear and tear$9,033,782
  3. Sewer projects paid with bonds and savings$17,997,731
  4. Full report budget$82,869,352
See the match for each fund
Each row adds to the full report budget.
FundService budgetWear and tearBonds and savings projectsFull report
Water$25,134,899$3,533,782$0$28,668,681
Sewer and storm drains$30,702,940$5,500,000$17,997,731$54,200,671

Wear and tear is called depreciation. It is an accounting cost, not a bill paid now.

EXPLORE THE TOTALS

Find a work area

CSV download pending

Choose a row to see each type of cost. These budgets use the same view as the cards above.

13 work areas · 48 cost groups

WATEROffice and shared costsService budget$3,069,709Costs recorded$721,002.17

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Water: Office and shared costs
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$1,333,163.00$350,272.87Not yet supplied
Loan payments$0.00$0.00Interest onlyNot yet supplied
Repairs and replacement$250,000.00$184,799.99Not yet supplied
Other costs$809,622.00$183,395.87Not yet supplied
Power and chemicals$16,380.00$2,533.44Not yet supplied
City services$660,544.00$0.00Not yet supplied
WATERBilling and customer serviceService budget$2,645,490Costs recorded$483,434.43

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Water: Billing and customer service
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$905,687.00$129,408.79Not yet supplied
Loan payments$421,064.00$13,264.14Interest onlyNot yet supplied
Repairs and replacement$1,022,245.00$119,813.60Not yet supplied
Other costs$296,494.00$220,947.90Not yet supplied
WATERIsland water sourcesService budget$2,297,522Costs recorded$307,757.67

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Water: Island water sources
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$782,649.00$159,709.46Not yet supplied
Loan payments$752,272.00$26,010.75Interest onlyNot yet supplied
Repairs and replacement$444,154.00$78,388.55Not yet supplied
Other costs$150,516.00$37,143.24Not yet supplied
Power and chemicals$167,931.00$6,505.67Not yet supplied
WATERMainland water sourcesService budget$412,200Costs recorded$127,527.41

No purchase orders are included.

Water: Mainland water sources
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$56,057.00$32,387.27Not yet supplied
Repairs and replacement$50,000.00$0.00Not yet supplied
Other costs$24,190.00$3,966.67Not yet supplied
Power and chemicals$281,953.00$91,173.47Not yet supplied
WATERNewport water plantService budget$4,528,901Costs recorded$780,785.12

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Water: Newport water plant
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$1,278,192.00$275,591.88Not yet supplied
Loan payments$1,795,685.00$236,505.82Interest onlyNot yet supplied
Other costs$379,858.00$132,210.22Not yet supplied
Power and chemicals$1,075,166.00$136,477.20Not yet supplied
WATERLawton Valley water plantService budget$6,622,553Costs recorded$993,908.52

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Water: Lawton Valley water plant
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$1,340,841.00$268,682.23Not yet supplied
Loan payments$3,416,717.00$456,134.30Interest onlyNot yet supplied
Other costs$708,521.00$114,491.37Not yet supplied
Power and chemicals$1,156,474.00$154,600.62Not yet supplied
WATERWater testingService budget$445,827Costs recorded$74,506.70

No purchase orders are included.

Water: Water testing
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$276,965.00$60,113.39Not yet supplied
Other costs$168,862.00$14,393.31Not yet supplied
WATERWater pipesService budget$4,822,697Costs recorded$960,377.92

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Water: Water pipes
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$1,510,727.00$199,251.42Not yet supplied
Loan payments$676,379.00$103,747.06Interest onlyNot yet supplied
Repairs and replacement$2,202,638.00$468,631.73Not yet supplied
Other costs$404,236.00$186,244.97Not yet supplied
Power and chemicals$28,717.00$2,502.74Not yet supplied
WATERFire protectionService budget$290,000Costs recorded$4,908.49

No purchase orders are included.

Water: Fire protection
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
Repairs and replacement$200,000.00$0.00Not yet supplied
Other costs$90,000.00$4,908.49Not yet supplied
SEWER AND STORM DRAINSCapital workService budget$7,668,296Costs recordedNot available

This plan leaves out $17,997,731 of projects paid with bonds and savings. Project costs cannot yet be split between these sources.

Sewer and storm drains: Capital work
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
Repairs and replacement$7,668,296.00Not availableNot yet supplied
SEWER AND STORM DRAINSSewer plant, loans and shared costsService budget$18,409,420Costs recorded$3,443,508.77

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Sewer and storm drains: Sewer plant, loans and shared costs
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$1,610,490.00$209,685.29Not yet supplied
Loan payments$4,923,250.00$681,837.04Interest onlyNot yet supplied
Other costs$1,576,151.00$608,370.61Not yet supplied
Electricity$873,979.00$181,475.65Not yet supplied
City services$1,040,224.00$432,894.00Not yet supplied
Run the sewer plant$8,385,326.00$1,329,246.18Not yet supplied
SEWER AND STORM DRAINSSewer pipesService budget$1,627,288Costs recorded$220,834.96

No purchase orders are included.

Sewer and storm drains: Sewer pipes
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$945,222.00$130,794.64Not yet supplied
Other costs$682,066.00$90,040.32Not yet supplied
SEWER AND STORM DRAINSStorm drainsService budget$2,997,936Costs recorded$172,285.12

Loan costs show interest only. Principal paid is not shown. No purchase orders are included.

Sewer and storm drains: Storm drains
Type of costService budget · FY2027Costs recorded · FY2027Same dates · FY2026
People$947,740.00$115,462.74Not yet supplied
Loan payments$1,354,877.00$0.00Interest onlyNot yet supplied
Other costs$695,319.00$56,822.38Not yet supplied

There are no names or individual payments in these totals.

THE SAME DATES, LAST YEAR

A fair look at change

FY2026 costs for the same dates are not yet supplied. We will not compare a full year with part of a year.

See more: how to read the numbers

Annual service budget

The plan covers July 1, 2026 to June 30, 2027. Finance confirmed on October 30, 2026 that these are the adopted budget amounts, with no changes since. Wear and tear and sewer projects paid with bonds and savings appear only in the bridge.

Costs recorded

These are entries for July through September in the October 30 ledger. Late entries may be included. Open purchase orders are not shown. A zero means no net cost was found in the supplied entries.

Loan payments

The budget includes principal and interest. The cost figures show interest only. They do not show all loan payments. Principal paid must be checked against payment records.

Sewer project costs

Projects include new pipes, pumps and major repairs. Sewer project costs are not yet available. We cannot yet split them by how they are funded. Missing figures are not zero.

No progress bar

Costs do not arrive at a steady pace. Some payment figures are still missing. A small cost does not mean less work was needed or that money is free to spend.

Source and updates

Munis budget reports and account trial balances exported October 30, 2026. Costs use fiscal periods 1 through 3. The quarter was rebuilt from a later ledger. We still need to check the period, any missing entries and loan payments.