St. Mary’s and Sisson Ponds Floating Solar Project

Home / Water Division / NWD Capital Improvement Projects / St. Mary’s and Sisson Ponds Floating Solar Project

NWD Source Water Project

St. Mary’s and Sisson Ponds Floating Solar Project

Concept and Preapplication Review

  • Project TypeSource water management and renewable energy
  • Current PhaseConcept. Preapplication review with the Town of Portsmouth.
  • LocationSt. Mary’s Pond and Sisson Pond, Portsmouth, Rhode Island
  • Project TeamCity of Newport (owner). Laketricity and BlueWave (developers).

Project Overview

The City of Newport is evaluating a proposal to place floating solar panels on part of St. Mary’s Pond and Sisson Pond in Portsmouth. Both ponds are owned by the City and are active parts of the Newport Water supply. St. Mary’s Pond is about 100 acres and Sisson Pond is about 65 acres.

The project would be developed, built, owned, operated and removed at the end of its life by two private companies, Laketricity USA and BlueWave. The City would keep ownership of the ponds and lease space on them to the developers. The City selected the team through a request for qualifications and proposals.

The project is a concept. No permit application has been filed, no approval has been issued, and the size and layout are not final.

Drinking water comes first. Newport is evaluating this project mainly for what it could do for the reservoirs. Electricity would be a second benefit. Under the proposal, power generation would always rank below drinking water operations and drinking water rules.

Why Newport Is Considering This

Newport’s reservoirs are surface water supplies. In warm months, sunlight and heat drive algae growth and water loss, and algae adds treatment cost. Shading part of the water surface is intended to:

  • Lower the heat the reservoir takes in and steady the temperature of the upper water.
  • Reduce the light that algae need to grow.
  • Reduce water lost to evaporation, which matters most in a drought.
  • Produce renewable electricity without clearing land in the watershed.

These are expected benefits. They have not been measured at these ponds. The size of any water quality benefit depends on the final design and how much of each pond is covered, and Newport would monitor the ponds to check actual results.

What Is Proposed

  • Solar panels mounted on plastic floats made of high density polyethylene, the same family of plastic used for water pipe.
  • Floats anchored to the bank or the pond bottom. The array rises and falls with the water level.
  • Panels that sit about 20 inches above the water surface, with a glare reducing coating.
  • Electrical equipment on City land between the two ponds: small inverter and transformer pads along the existing access road and one interconnection area of about 10,000 square feet near the existing overhead power lines.
  • A direct connection to the electric grid. No battery storage is proposed.
  • Removal of the system and restoration of the site at the end of the project.

The developers’ preliminary concept presented to the Town of Portsmouth totals about 43 megawatts of peak capacity: about 21 megawatts on Sisson Pond and about 22 megawatts on St. Mary’s Pond. On Sisson Pond the preliminary layout shows arrays over about 35 acres, a little more than half of the pond surface. The array area on St. Mary’s Pond is being confirmed with the developers and will be posted here.

These figures are preliminary. Size, layout and the share of each pond that is covered may change through design, water quality review and permitting.

What Newport Keeps Control Of

The City owns the ponds and would keep authority over:

  • Reservoir operations and water levels
  • Source water quality and monitoring
  • Dam safety
  • Site security and emergency access
  • The primary purpose of the ponds as a public drinking water supply

Parts of the system that touch the water must be suitable for contact with drinking water. The developers have provided test documentation under British Standard BS 6920, a standard for materials in contact with drinking water. Newport and state regulators will review materials, monitoring and operating controls before any approval.

Funding and Cost

The project is proposed with no capital investment by the City or by Newport Water customers. The developers would pay to design, permit, build, operate and remove the system and would lease space on the ponds from the City.

  • The lease term discussed is at least 20 years, with possible extensions.
  • Payments to the City would depend on the final size of the project. No amount is final.
  • The developers would be required to post financial guarantees, including one that covers removal of the system.
  • How the electricity would be sold has not been decided.

Schedule and Current Status

Status as of November 16, 2026: The project is in preapplication review with the Town of Portsmouth. The Town has not yet determined which review process applies. No application has been filed and no hearing date has been set.

Project milestones to date
DateMilestone
October 2023The City and BlueWater Energy Partners, the developers’ joint venture, signed an option agreement for a possible lease on the ponds.
February 25, 2026The City and the developers introduced the concept to Town of Portsmouth officials.
July 2026The developers asked the Town for guidance on the permitting pathway. Newport stated its position that the project should be reviewed as a public water utility and reservoir management facility.
September 23, 2026Follow up meeting among the Town, the City and the developers.
October 26, 2026Newport Water sent a letter of support to the Portsmouth Town Planner.
October 27, 2026Preapplication review by the Portsmouth Technical Review Committee for initial feedback.
November 12, 2026Informal preapplication discussion with the Portsmouth Planning Board. The Board took no vote.
NextTown determination of the review process, a formal application by the developers, state agency review, and public hearings. No dates are set.

Permitting and Review

The ponds are in Portsmouth, so the Town of Portsmouth decides the local land use questions. Portsmouth’s zoning ordinance does not list floating solar as a use. The Town is working out which process applies. The options under discussion include a special use permit, review by the Planning Board, treatment as a public utility use, or an amendment to the zoning ordinance.

Other reviews are expected to include:

  • Rhode Island Department of Environmental Management
  • Rhode Island Department of Health, Center for Drinking Water Quality
  • Aquidneck Land Trust, which holds a conservation easement, for consistency with that easement
  • The electric utility, for the grid connection

The specific permits and their order have not been confirmed. This page will list each one as it is identified.

Questions Raised So Far

Will the panels be visible?

The developers prepared a preliminary visual assessment from seven public viewpoints on Jepson Lane, Sisson Pond Road, Union Street and Carriage Drive. It shows the array as not visible from four viewpoints and partly visible as a thin, low line on the water from three. Winter views with leaves down may show more. The assessment is based on a preliminary design and will be updated.

Will there be noise?

Noise from the electrical equipment has not been studied yet. A noise study would be part of a formal application.

Where will the power go?

The system would connect to the electric grid. How the power would be sold has not been decided.

What happens when the water is low or frozen?

The floats move with the water level. Design for low water, ice and snow at these ponds will be addressed in the formal application.

Has this been done on drinking water reservoirs before?

The developers cite operating floating solar systems at water utilities, including Sayreville, New Jersey, in service since 2019, and Windsor, California, in service since 2020. Newport will rely on its own review and on state regulators and not only on those examples.

Project Documents

The presentation given to the Portsmouth Technical Review Committee and Planning Board, which includes the preliminary layouts and the visual assessment, is being prepared for posting on this page. To request a copy now, call the Department of Utilities at 401-845-5600.

What This Means for the Public

Nothing changes today. The ponds continue to operate as drinking water reservoirs, and this project does not affect water service, water quality or water rates at this stage.

Decisions on local approval will be made in public by the Town of Portsmouth. Residents will be able to comment at public hearings once an application is filed.

  • Questions about Portsmouth’s review: Town of Portsmouth Planning Department, 401-643-0332.
  • Questions about the reservoirs and Newport’s role: Newport Department of Utilities, 401-845-5600.

Project Partners

  • Owner: City of Newport, Department of Utilities, Newport Water Division
  • Developers: Laketricity USA and BlueWave. They would own and operate the solar system. The City would lease them the space on the ponds and would not own the equipment.
  • Host community and local review: Town of Portsmouth
  • State agencies: Rhode Island Department of Environmental Management and Rhode Island Department of Health
  • Conservation easement holder: Aquidneck Land Trust

Last updated November 16, 2026. This page summarizes a proposal that is still a concept. Information is updated as design, permitting and agreement milestones are reached. For questions, please contact the Newport Department of Utilities at 401-845-5600.